this post was submitted on 20 Jun 2025
162 points (98.2% liked)

Sysadmin

9910 readers
1 users here now

A community dedicated to the profession of IT Systems Administration

No generic Lemmy issue posts please! Posts about Lemmy belong in one of these communities:
!lemmy@lemmy.ml
!lemmyworld@lemmy.world
!lemmy_support@lemmy.ml
!support@lemmy.world

founded 2 years ago
MODERATORS
 

So that's why a 2 systems were getting crappy speeds. Yes, 2. It had been used only to split a single drop from another switch between two systems.

New drop, happy clients.

Some stuff here is museum material.

you are viewing a single comment's thread
view the rest of the comments
[–] RunJun@lemmy.dbzer0.com 23 points 5 days ago (9 children)

Shouldn’t be a grounding issue as you said that you buried it.

[–] GreatBlueHeron@lemmy.ca 2 points 5 days ago (7 children)

It's a 200' cable and the buildings each have their own connection to the power company. I suspect that the earth potential of the two buildings is quite different - I just have not figured out a way to measure it yet and not sure if there's anything I can do to fix it even if I do confirm it.

[–] PlutoniumAcid@lemmy.world 2 points 4 days ago (1 children)

Pull a copper wire from one ground to the other?

[–] GreatBlueHeron@lemmy.ca 1 points 4 days ago

I guess that's what I haven't figured out yet - it's about 200' and I don't have 200' of wire laying around. I'm thinking of making dummy terminations for each end of my cat6 cable and stripping each of the pairs and twisting them together so it works as a single conductor and using that to measure.